wesernetz Bremen GmbH operates the power and water supply networks in Bremen. In the wake of coal phase-out, hard-coal-fired power plants in Bremen will be shut down. Part of the required district heat will be gained from an improved use of energy from waste. For this purpose, wesernetz Bremen plans and constructs a district heating connection line between two hitherto independent networks.
The district heating connection line, consisting of two DN 500/710 plastic-coated lines (supply and return) and a planned length of 7.5 km, is located within the city and is to connect the existing waste-to-energy plant Bremen with the heating plant Vahr.
The technical design includes structural engineering, district heating systems engineering, inner-city water supply and sanitation, coordinated planning of existing and new utility lines, as well as the planning of excavation trenches and associated supporting systems, pipe driving, and the preparation of the application for pipeline crossing under railway tracks of the German railway company DB.
Within the scope of site management and construction supervision, the Consultant supervised two construction companies, four construction lots, and up to eight construction sections in parallel.